During the course of the coming week, Transport for Buckinghamshire will be carrying out work in the following places as part of the Strategic Highway Maintenance Programme. As some activities depend on the weather, dates shown are subject to change at short notice.

No weekend working is planned. 

Carriageway surfacing

BridgeStreet / Church Street, Great Kimble  –  A4010 to B4009 (20/05/19 to 24/05/2019)

Conventional resurfacing taking place using a day time road closure between 07:00 and 19:00hrs. Temporary 2 way traffic signals will also be in use temporarily at the junctions with the A4010 & B4009.

Blackpond Lane, Farnham Royal – Hawthorn Lane and Farnham Lane (20/05/2019 to 24/05/2019)

Surface dressing preparatory patching works taking place using a day time road closure between 07:00 to 19:00hrs.

Forty Green Road, Knotty Green - Penn Road to Royal Standard PH (20/05/2019 to 28/05/2019)

Surface dressing preparatory patching works taking place using a day time road closure between 07:00 to 19:00hrs.  

Greenlands , Lacey Green - Loop of roundabout – (20/05/2019 to 21/05/2019)        

Hand-lay micro surfacing preparatory works taking place using a day time road closure between 07:30 to 17:30hrs.

Carriageway surfacing – Plane and Patch programme

Orchehill Avenue, Gerrards Cross - wholeRoad (20/05/2019 to 21/05/2019)  

Plane and Patch works taking place using a day time road closure between 08:00 and 17:00hrs.

Hammersley Lane, High Wycombe – whole length (20/05/19 to 23/05/19)

Plane and Patch works taking place using a day time road closure between 08:30 and 15:30hrs.

Whielden Close, Amersham - whole road (22/05/2019 to 22/05/2019) 

Plane and Patch works taking place using a day time road closure between 08:00 and 17:00hrs.

Stoke Green , Stoke Poges -  whole road (23/05/2019 to 30/05/2019)  

Plane and Patch works taking place using a day time road closure between 09:30 and 15:30hrs.

Footway surfacing

High Street, Chesham – White Hill to The Broadway (20/05/2019 to 24/05/2019)          

Footway block paving works taking place using localised traffic management between 08:30 and 03:00hrs.

Drainage work

Marlow Bottom Road, Marlow Bottom – Marlow Bottom to Brucewood Parade (20/05/2019 to 24/05/2019)

Minor drainage works taking place using 2 way traffic signals between 09:30 and 17:30hrs.